Frequently Asked Questions

What is the Force 10 Buliding System best suited for?  

What does a Force 10 building cost?

What is the Force 10 Guarantee?

Can homes be built on steep or remote sites?

Can I use my own builder or build it myself?

How long does it take for the Force 10 package to arrive on site?

How long will it take to build a Force 10 house?

Why is Force 10 better than conventionally built buildings?

Is Force 10 a "pre-fab" or "kit" home?

Does a Force 10 home look different than a timber or brick/block home?

What effect does the coastal environment have on Force 10 buildings?

How do I hang a picture on a wall?

What is the Force 10 Building System best suited for?

Force 10 is a building system that has been engineered to provide a superior structure in environments subjected to cyclonic force winds and earthquakes. It is best suited for regional areas that are subjected to these environmental conditions and other remote locations in Australia and the world where transportation of building products is a costly exercise. FORCE 10 package the whole, complete building into one delivery, frequently in a secure container, to ensure the complete building reaches the site for construction.

Because everything for the building is delivered in one go, the time of the builder and trade person on site is minimised as there is no delay in waiting for different trades to turn up at the site. This can save an enormous amount of on “site time”.

In addition because Force 10 is a bolt together/ tex screw fixing system, the buildings are fast to install and can be completed by a team of semi skilled persons lead by an experienced builder. This reduces both time and labour construction costs on site and provides the economies achieved by the FORCE 10 Building System.

The FORCE 10 Building system uses environmentally friendly materials that are safe, strong, and resistant to fire, termites and rot. Because it is a component system, it can be utilized to develop almost any building plan, both residential and commercial.

Force 10 buildings are also ideal for schools, clinics, government buildings, resorts, mining camps in remote areas where conventional building is sometimes difficult and slow to achieve because of long transportation distances. All Force 10 buildings are considered low maintenance buildings once completed.                                                         

>back to top

What does a Force 10 building cost?

FORCE 10 buildings are quite cost competitive when compared to conventionally built homes that are constructed to an equivalent engineering standard. FORCE 10 use quality materials and our finished product is superior to most other building systems. Material supply costs may be less in some locations for locally sourced materials, but availability is frequently an issue. With Force 10, availability is not an issue because everything is supplied for the building at the cheaper capital city prices. There are freight costs for delivery of FORCE 10 depending on location and remoteness of the project, but local material suppliers have to include freight, storage and handling costs in their local prices.

In remote locations where these tradesmen are hard to find, it is often more economic to bring in such trades people as part of the building team, because they are on site when you need them and the job is finished. However if local trades people are available at the time, it is often preferable to use the local resources.

Fit Out costs such as painting, tiling, cabinets, custom windows and doors are a function of the quality of interior finishes required by the owner and would be the same whether the frame of the house is made from conventional building materials or FORCE 10 building material. Force 10 buildings usually cost less to complete to lock up compared to other buildings methods when building to an equivalent finished quality and engineering standard.

Your local North Queensland FORCE 10 Dealer can assist you to have your house plans slightly amended to suit the FORCE 10 Building System, obtain a free quote for the FORCE 10 component, ex factory, and can advise on building and freight costs or put you in touch with a trained and approved FORCE 10 Builder to assist you in the construction of your house or building.

Please visit our contact us page to enquire or click here.                                                                                                                           

>back to top

What is the Force 10 Guarantee?

The Force 10 Building system is engineer designed and certified to the Australian Standard Wind Code AS 1170.2 for the regional design wind speeds specified in the code. It can be shown that forces from these winds are also equivalent to seismic forces due to earthquakes. In Australia and New Zealand, buildings in known earthquake regions must also be designed to the Australian Code for Earthquake loading. FORCE 10 performs well structurally in either condition.

FORCE 10 provides a 10 year structural warranty and certificate by a certified structural engineer, as well as, a product component guarantee. All the structural materials are covered by manufacturer's worldwide warranties and guarantees. All manufacturing is undertaken according to N.C.S. International Certified Quality Management System, ISO 9001. We have never lost a roof anywhere in the world. No other system-built home can make these claims.  
                                                                                               

>back to top

Can homes be built on steep or remote sites?

Force 10 structures have been built in many locations considered too difficult to build on or where conventional construction would take considerably longer to build. We can build with the Force 10 System on any site and at any location where our building materials can be delivered, whether by container, truck, boat, helicopter or by road. By utilizing our steel floor system, the excavation and foundation work is kept to a minimum and typically eliminates the need for heavy equipment.             

>back to top

Can I use my own builder or build it myself?

It is recommended that you utilise an accredited FORCE 10 builder to assist you with the construction of the project, which may only mean the services of one accredited person. If you and your friends have reasonable skills, then you should be capable of providing the remainder of the labour force required for the work.

In Queensland, you need to be registered as an Owner Builder with the local government authority before you can build a house, otherwise you have to engage a registered builder to direct the work and sign off on the paperwork and achieve the approval of a local building certifier before the Local Government will issue you with an occupancy permit.

Your North Queensland dealer will be able to assist you in locating an accredited FORCE 10 builder.   
                                                                                                           

>back to top

How long does it take for the Force 10 package to arrive on site?

We currently manufacture Force 10 component packages in our production facilities in Brisbane, Queensland. A typical turn-around time is 6-8 weeks from the submission of a Request for Quotation until the Force 10 package is completed at the factory and ready for delivery. During this period, complete engineering drawings are produced and sent to the client for approval. Delivery time to site is a function of the distance and means of proposed transport to site. Each case has to be evaluated                                                                                          

>back to top

How long will it take to build a Force 10 house?

A typical three bedroom FORCE 10 house of 160 m2 is estimated to take 3-4 weeks to complete to Lock Up with a crew of 4-5 persons.

A typical site construction schedule will include the following activities :

  • The concrete slab may be prepared before material arrives on site.
  • Alternatively the holes for the galvanised steel stumps can be drilled or excavated before the material arrives on site. Allow two days with mechanical plant.
  • Unload the container and check all materials delivered. Allow one day.
  • Assemble galv. steel floor bearers and piers on cribbage and level floor. Pour concrete footings around steel stumps. Allow two days.
  • Install galv. steel floor joists and 16mm SUPA floor. Allow one day.
  • Assemble and install exterior and interior wall panels.Allow one to two days. (windows are pre- installed in panels at the factory).
  • Assemble and install galvanized steel roof trusses. Allow two days.
  • Install roof purlins, fascia and soffit. Allow three days.
  • Install roof insulation and sheeting.  Allow four days.
  • Electrical and plumbing rough-in. Allow three days.
  • Install ceiling, cornices, tape interior wall and ceiling joints. Allow four days.
  • Apply exterior acrylic plaster to walls while interior joints are  being finished. Allow three days.
  • Install pre-hung doors, skirting board and architrave. Allow four days.
  • House completed to lock up
  • Fit Out including painting, tile installation, cabinet installation, electrical and plumbing completed by local trades over a further 3 - 4 weeks.
 

Note: Construction time will vary with location, due to remoteness, number of persons in the team and their skill levels, site conditions and weather. A number of the activities listed above can be undertaken at the same time as other activities are being completed to bring the overall time to around 4 – 6 day weeks. The Force 10 component package described above includes all the materials needed to make the building weather-tight and complete to lock up stage.                                                                                                                

>back to top

Why is Force 10 better than conventionally built buildings?

Force 10 International engineers have spent millions of dollars and over ten years developing a building system that solves many of the problems associated with building in the regions plagued by natural disasters. They have developed a manufacturing technique that produces aesthetically pleasing and affordable buildings that will withstand these destructive forces of nature. FORCE 10 offers an excellent alternative building method that also reduces the risk of damage due to fire, rot and termites that can destroy conventionally constructed buildings that use timber framing. Force 10 homes also reduce the pressure on forest reserves for building materials and minimise construction waste.

>back to top

Is Force 10 a "pre-fab" or "kit" home?

Force 10 is an engineered building system that utilizes components manufactured to ISO 9001 Quality Assurance standards in a state-of-the-art production facility. All the components of the FORCE 10 system are ready for installation and require little to no additional work to complete an element or component. Kit or pre-fab homes provide framing that needs addition work on site work to complete the component, walls for example need external and interior cladding and sheeting applied separately. FORCE 10 walls are supplied with cladding , windows and doors already fitted.

The Force 10 Engineered System has three basic components: the floor system, wall system and roof system (see Features) all based on a 1 metre long wall module length Three standard wall panel heights are available. These components can be used to create an infinite number of floor plans and roof designs. We offer many choices in roof sheeting profiles and colours, as well as three attractive exterior wall finishes. The materials used in the Force 10 system are the highest quality available worldwide.

It is generally a simple matter for conventional house plans to be “FORCE 10 ized”, that is, to slightly change the dimensions of rooms and the overall building to fit in with the1 metre modularised wall panels. Frequently the overall dimensions of the house change only very slightly, whilst the interior dimension of the rooms increase because of the narrow FORCE 10 wall panel width.

Your North Queensland FORCE 10 Dealer will assist you in developing a “FORCE10ized” floor plan before sending it off for a Quote.

>back to top

Does a Force 10 home look different than a timber or brick/block home?

No. In fact many people comment that upon first visiting a completed home, they can't tell the difference between a conventionally built home and a Force 10 home. We have many satisfied homeowners who feel that their Force 10 home is superior in quality of finish and strength to other standard homes in their area. The finished Force 10 home is aesthetically pleasing and matches the prevailing architectural styles of the location where it is built. We encourage you to visit a Force 10 home to see first-hand the finished quality and engineered strength of every building. 

                                                                                                                                       >back to top

What effect does the costal environment have on the Force 10 building?

The coastal environment is one which occurs within a band of 2-3 km from the coastal shore line. This environment is frequently impacted by moist, salt laden air which can leave higher salt concentrations on buildings than other environments. Salt enhances the corrosive environment on structures, be they metal or concrete. For this reason home owners are advised to undertake regular maintenance of their properties by washing down their buildings with fresh water to remove the salt and extend the performance of the finishes on their homes.

The preferred method of protection of metal surfaces from corrosive environments, particularly steel and aluminium is achieved by suitably applied anti corrosive coatings at the point of manufacture.

The primary protective strategy of FORCE 10 is that all structural steel components of the FORCE 10 building system are protected by zinc galvanising as the steel strip or product passes through the manufacturing process. In particularly severe environments, steel components can be galvanised a second time before delivery, to provide a thicker layer of zinc protective material to the steel.

The second protective strategy applied by FORCE 10 Building systems is to ensure that wherever possible any steel component is adequately covered or enclosed to prevent exposure to the atmosphere, preventing the corrosive environment from contacting the steel. This is achieved by weather proof cover strips and applied coatings.

Roof and gutter products are similarly treated and covered by the manufacturers warranties.

    

>back to top

How do I hang a picture on a wall?

It is very easy to attach a picture, heavy mirror, or a cabinet to the Force 10 wall panel. Every wall surface, both interior and exterior, consists of a very strong fibre-cement sheet that can be used for attaching a variety of objects. In the case of heavy objects, fixings can be made through the steel studs at the perimeter of each panel. That stud can be found by a stud detecting meter.                                                                                    

>back to top

Force 10 North Queensland 2/57 Stagpole Street, West End, Townsville 4810 QLD  Phone: 07 4772 5990 

Mobile: 0429 616 618  Email:  peter@force10nq.com  

Easy Construction

Certified for Cyclonic & Seismic Conditions

Cost Competitive

Environmentally Friendly and Energy Efficient

Quality Guaranteed

Borer and Termite Resistant 

Fire Resistant and Flood Tolerant

Fast Construction Time Frame

Total Construction Solution

 

 

 

"Our system is capable of solving all logistical situations associated with the construction industry worldwide."